The demolition of Jacques Dube’s Square has been completed. Over the next few weeks, workers will be busy picking up the rest of the debris and then moving on to the next step.
According to the project manager at these two locations, Danny Morin, the steel structure installation of the buildings will be completed within the coming weeks.
Starting next week, on Mondays in Cabano, in the plaza, the installation of the steel structure will begin. And on December 6, it will start at the entertainment center in Notre Dame
, He says.
« It should all come to an end for the holidays. We hope so. It all depends on mother nature. If rain is declared, we cannot work with the structure. By Christmas, we’ll really see the building’s skeleton. »
The costs of the projects for the plaza and the multifunctional center in Témiscouata-sur-le-Lac are estimated at $21.5 million.
Construction work began last May.
Based on information from Patrick Bergeron

Natalie Sinclair is a contributor at Vaughantoday.ca, covering a wide range of topics including local news, politics, business, technology, sports, entertainment, and lifestyle. She focuses on delivering clear, accurate reporting and useful information that helps readers stay informed about current events and issues that matter to their communities. Her work highlights timely developments, relevant stories, and practical insights in a professional and reader-friendly manner.